Project: Demolition of Knottingley Swimming Pool & Leisure Centre
Client: Wakefield Council
Location: Wakefield
Date: March 2018

Ron Hull Demolition Ltd were appointed as Principal Contractor following an intense tender period with Wakefield Local Authority. 

Scope of Works

The project was split into 5 phases;

Phase 1 – Asbestos Removal

Undertaken by a Specialist framework partner.

Phase 2 – Soft Strip

Throughout the Leisure Centre, stockpiling for removal into relevant skips.

Phase 3 – Decommissioning

Samples were taken from tanks on site and tested. Fluids were then removed inhouse by our Decontamination team, prior to the tank Demolition.

Phase 4 – Demolition

The 4 storey, concrete framed building was demolished using remote techniques with various excavators.

Phase 5 – Crushing

Crushing was then undertaken onsite, producing aggregate to 6F2.

Project Challenges

  • Within a Residential Housing Estate

  • Close proximity to Social Club neighbours

  • Adjacent to live main road